The new, two-phase South Ferry Terminal Project will include
the construction of a new tunnel and station platform. The Phase 1 tunnel
construction is being performed by a joint venture of Schiavone Construction
and Granite Construction and will be completed by the end of 2007. The
Phase 2 portion of the project will consist of fitting-out the tunnel
and platform in an aggressive 22-month schedule. Five Star’s electrical
contract provides all the electrical work which includes new electric
service and distribution, panels, signals, communication systems, fan
plants, DC control work, fire alarms, lighting fixtures and various low
voltage systems. Judlau Contracting, Inc. is the prime general contractor
with MTA Capital Construction, who also serves as the architect and engineer.